Uttarakhand Integrated Urban Development Project (UIUDP)

 

DEA-GoI accorded financial assistance approval from ADB of Total Outlay US$ 250 Million [80(US$ 200m) :20(US$ 50m)] on dated: 18.03.2018 in 2 Tranches of US$ 100 Million financial assistance.

 

Urban Infrastructure of 06 major towns (Dehradun, Roorkee, Kotdwar, Nainital, Ramnagar and Haldwani) to be developed.

 

First Phase : US$ 150 Million sub-projects(Dehradun & Nainital Towns) finalized with ADB.

 

Second Phase: US$ 100 Million DPRs are ready and submitted to Planning Dept. GoU for review.

 

Detailed planning for Water Supply and Sewerage of Roorkee, Kotdwar, Nainital, Ramnagar and Haldwani Towns completed.

 

Planning of Dehradun Water Supply and Sewerage System under progress in consultation with UPJN, Jal Sansthan & DSCL.

 

Advance Contracting Approval from ADB has been received in the month of October 2020.

 

3 packages bids (Raipur, THDC & Nainital Sewerage) tenders has been floated in January 2021, and rest bids will be floated soon.

 

Project Processing Schedule by ADB and agreed in TPRM dated: 28.10.2020 is as follows:

Milestones                                            Expected Completion Date
1. Project fact Finding Mission                    March 2021
2. ADB Staff Review Meeting                      May 2021
3. Loan Negotiations                                   June 2021
4. Loan Approval                                         August 2021